Word Problems Drills
By Elias Saab and Daniel E. Saab.
(Copyright saab.org 1998-2010)


New Problem:
The first painter can finish a paint job in 8 hours. The second painter can finish the same job in 4 hours. How long would it take them to finish the job if they are working together. You can give the answer as a fraction m/n.

Write your answer below: